Construction of the Garrison Church of St. Martin in Koszalin

Completion period

2021 - 2023

Location

Koszalin, Zwycięstwa Street

Investor

Regional Infrastructure Authority in Szczecin

Delivery model

General contracting

Project type

Religious building

Project description

Telmax completed the construction of the Garrison Church of St. Martin in Koszalin. The project included the construction of a new religious building together with complete technical infrastructure, site development works and the demolition of the existing garrison chapel.

The project required efficient coordination of construction, installation and external works specific to a building with a specialised function. The new church was designed to serve both the military community and the civilian parish of St. Martin.

Scope of works

As part of the project, Telmax was responsible for, among other things:

  • construction and structural works,
  • construction of the new church building together with the tower,
  • installation of internal building systems,
  • construction and redevelopment of external utility networks and connections,
  • installation of sanitary and stormwater drainage systems together with a retention system,
  • installation of water, gas, heating and electrical infrastructure,
  • installation of telecommunications infrastructure,
  • demolition of the existing garrison chapel,
  • construction of new paved surfaces and parking areas,
  • construction and redevelopment of fencing,
  • installation of small architectural elements,
  • landscaping and restoration of green areas,
  • preparation of the building for handover and use.

Construction summary

The project involved the comprehensive construction of a new building together with an extensive scope of technical infrastructure and development of the surrounding area. The individual stages required precise coordination of structural, installation and finishing works, as well as the integration of the new infrastructure with the existing utility networks within the military complex.

Telmax was responsible for organising and coordinating the works covered by the contract and managing the construction process through to the stage enabling the church to be put into use. Particular importance was placed on delivering a building with distinctive architecture and specific functional requirements, while at the same time comprehensively developing and organising its immediate surroundings.

The completed project resulted in a modern Garrison Church which, together with the new infrastructure, parking facilities and landscaped surroundings, created a functional space for both the military community and the residents of Koszalin. The church was officially consecrated on 16 June 2024.

Need a partner to implement a similar investment? Let's talk about your project.

They trusted us

We have over 100 partnerships and projects behind us that will last for years.

A partner you
‍can rely on

Every good project starts with a conversation. Whether you're planning a new investment, need service support,
or are looking for a trusted technology partner, we're ready to get started.

‍We combine knowledge, experience, and a practical approach to execution. Email or call us — we'll get back to you with a specific answer.

Send inquiry

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Telmax is part of the group:

Address